Camden1

St George

Demolition
28 February, 2022

Contract Period:

15 Weeks

Overview

Demolition and site clearance of the former Morrison’s superstore and excavation around the historical arches.

Camden1

Challenges

Working on a large site surrounded on all sides with residents, businesses and live rail way lines, one being the main line into London Euston. 

Camden2

Actions

We provided detailed Method Statements, including noise, dust, and vibration monitoring across the site for the duration of the demolition phase. A Vacuum Excavator was used to expose the historical arches so they could be checked by the Structural Engineers. As the aches were still in use, we very carefully diamond cut them back in readiness for the new development to be built. 

Results

Our pre-planning and hard work made this demolition, site clearance and excavation, a very successful project. 

Camden3